Substation Scout

Washington Energy Facility

PJM queue ID AA1-014

Washington Energy Facility (AA1-014) is listed in the PJM interconnection queue as a 5 MW gas project in Washington County, OH. The filing names Washington as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of October 1, 2015.

Queue IDAA1-014
Project nameWashington Energy Facility
Status (as published)In Service
SubstationWashington
Point of interconnectionWashington 345kV
CountyWashington
StateOH
Voltage345 kV
Capacity5 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2015-10-01
Source datasetserial

Same substation and county

Washington substation: 3 requests in the PJM queue, 3 active totaling 53.3 MW.

Queue IDProjectMWResourceStatus
AA2-141Washington Energy Facility45GasIn Service
W3-044McCullough Road Solar Farm3.3SolarIn Service

Washington, OH: 14 requests in the PJM queue, 7 active totaling 180.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy5
MW capacity5
MFO625

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.