McCullough Road Solar Farm (W3-044) is listed in the PJM interconnection queue as a 3.3 MW solar project in Warren County, NJ. The filing names Washington as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 30, 2019.

Queue IDW3-044
Project nameMcCullough Road Solar Farm
Status (as published)In Service
SubstationWashington
Point of interconnectionWashington 34.5kV
CountyWarren
StateNJ
Voltage34.5 kV
Capacity3.3 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2019-06-30
Source datasetserial

Same substation and county

Washington substation: 3 requests in the PJM queue, 3 active totaling 53.3 MW.

Queue IDProjectMWResourceStatus
AA2-141Washington Energy Facility45GasIn Service
AA1-014Washington Energy Facility5GasIn Service

Warren, NJ: 113 requests in the PJM queue, 24 active totaling 353.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy8.8
MW capacity3.34
MFO8.8

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first