Washington, OH interconnection queue

7 active projects totalling 180.5 MW in the PJM queue, plus 7 with terminal status (shown greyed).

7active projects
180.5active MW
14total filed
Queue IDProjectkVMWResourceStatus
AD1-090 Muskingum River 345 kV Phase I 345 1,180 Gas Withdrawn
AD1-091 Muskingum River 345 kV Phase II 345 590 Gas Withdrawn
AH1-449 Muskingum River - Sporn 345 kV 345 150 Hybrid Withdrawn
Z2-112 Waterford 345kV 345 64.5 Gas In Service
X4-003 Mill Creek-Riverview 138kV 138 56 Gas Withdrawn
AA2-141 Washington Energy Facility 345 45 Gas In Service
AH1-719 Beverly 345 kV 345 21 Gas Active
S35 Washington Energy Facility 345 20 Coal In Service
T164 Muskingum River #5 n/r 15 Coal In Service
R87 Muskingum River #5 n/r 10 Coal In Service
Z2-032 Clean River Power MR-1 (Devola) n/r 5.2 Hydro Withdrawn
Z2-033 Clean River Power MR-2 (Lowell) n/r 5.2 Hydro Withdrawn
AA1-014 Washington Energy Facility 345 5 Gas In Service
Z2-034 Clean River Power MR-3 (Beverly) n/r 4 Hydro Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.