Substation Scout

Muskingum River #5

PJM queue ID R87

Muskingum River #5 (R87) is listed in the PJM interconnection queue as a 10 MW coal project in Washington County, OH. PJM lists its status as “In Service”, with a target commercial operation date of April 1, 2007.

Queue IDR87
Project nameMuskingum River #5
Status (as published)In Service
SubstationMuskingum River #5
Point of interconnectionMuskingum River #5
CountyWashington
StateOH
VoltageNot reported
Capacity10 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Target commercial operation2007-04-01
Source datasetserial

Same substation and county

Washington, OH: 14 requests in the PJM queue, 7 active totaling 180.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy10
MW capacity10
MFO585

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.