Substation Scout

AD2-066 Tap (Hog Run Creek Switchyard ) 138 kV

PJM queue ID C01-1711

AD2-066 Tap (Hog Run Creek Switchyard ) 138 kV (C01-1711) is listed in the PJM interconnection queue as a 75 MW hybrid project in Grundy County, IL. The filing names AD2-066 Tap (Hog Run Creek Switchyard ) as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2030.

Queue IDC01-1711
Project nameAD2-066 Tap (Hog Run Creek Switchyard ) 138 kV
Status (as published)Active
SubstationAD2-066 Tap (Hog Run Creek Switchyard )
Point of interconnectionAD2-066 Tap (Hog Run Creek Switchyard ) 138 kV
CountyGrundy
StateIL
Voltage138 kV
Capacity75 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalized for filtering)
Target commercial operation2030-12-01
Source datasetcycle

Same substation and county

Grundy, IL: 44 requests in the PJM queue, 18 active totaling 3,015.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperRWE Solar Development,LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy150.0
MW capacity75.0
MFO150.0
Submitted date4/24/2026
Last updated6/24/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.