Zenaida Bus# substation interconnection queue

2 active projects totaling 247.5 MW in the ERCOT queue.

2 ERCOT queue filings name Zenaida Bus# as the point of interconnection, all in Duval County, TX.

Target commercial operation date as filed: Sep 2029 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Dove Wing Energy Center, LLC (2 filings).

2active projects
247.5active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
26INR0391 Jumping Cactus Storage 138 125.3 Battery SS Completed, FIS Started, No IA Sep 2029
26INR0393 Dove Wing Storage 138 122.2 Battery SS Completed, FIS Started, No IA Sep 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Duval County, TX

All 18 ERCOT queue filings in Duval County, TX.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first