Tap Bus # Miguel5 - Bus # Cruce7A Ckt 1 substation interconnection queue

3 active projects totaling 1,157.9 MW in the ERCOT queue.

3 ERCOT queue filings name Tap Bus # Miguel5 - Bus # Cruce7A Ckt 1 as the point of interconnection, all in Duval County, TX.

Target commercial operation date as filed: Mar 2029 (3 filings). 3 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Cielo Vista Solar, LLC (1 filing), Cielo Vista Power, LLC (1 filing), Cielo Vista Storage, LLC (1 filing).

3active projects
1,157.9active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
27INR0150 Cielo Vista Solar 345 503.3 Solar SS Completed, FIS Started, No IA Mar 2029
28INR0325 Cielo Vista Power Gas Plant 345 343.8 Gas SS Completed, FIS Started, No IA Mar 2029
29INR0115 Cielo Vista Storage 345 310.8 Battery SS Completed, FIS Started, No IA Mar 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Duval County, TX

All 18 ERCOT queue filings in Duval County, TX.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first