Tap Bus # Miguel5 - Bus # Cruce7A Ckt 1 substation interconnection queue
3 active projects totaling 1,157.9 MW in the ERCOT queue.
3 ERCOT queue filings name Tap Bus # Miguel5 - Bus # Cruce7A Ckt 1 as the point of interconnection, all in Duval County, TX.
Target commercial operation date as filed: Mar 2029 (3 filings). 3 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Cielo Vista Solar, LLC (1 filing), Cielo Vista Power, LLC (1 filing), Cielo Vista Storage, LLC (1 filing).
3active projects
1,157.9active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 27INR0150 | Cielo Vista Solar | 345 | 503.3 | Solar | SS Completed, FIS Started, No IA | Mar 2029 |
| 28INR0325 | Cielo Vista Power Gas Plant | 345 | 343.8 | Gas | SS Completed, FIS Started, No IA | Mar 2029 |
| 29INR0115 | Cielo Vista Storage | 345 | 310.8 | Battery | SS Completed, FIS Started, No IA | Mar 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Duval County, TX
- Tap (Cruce) - (San Miguel) Ckt 1: 2 active, 401.6 MW of 2 filed
- Zenaida Bus#: 2 active, 247.5 MW of 2 filed
- Bruni (#) – Crestonio (#) line; AEP: 1 active, 0 MW of 2 filed