Substation Scout

Jumping Cactus Storage

ERCOT queue ID 26INR0391

Jumping Cactus Storage (26INR0391) is listed in the ERCOT interconnection queue as a 125.3 MW battery project in Duval County, TX. The filing names Zenaida Bus# as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 30, 2029. It records the screening study as complete on March 19, 2024.

Queue ID26INR0391
Project nameJumping Cactus Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationZenaida Bus#
Point of interconnection138 kV Zenaida Bus# 80043
CountyDuval
StateTX
Voltage138 kV
Capacity125.3 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-09-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Zenaida Bus# substation: 2 requests in the ERCOT queue, 2 active totaling 247.5 MW.

Queue IDProjectMWResourceStatus
26INR0393Dove Wing Storage122.2BatterySS Completed, FIS Started, No IA

Duval, TX: 18 requests in the ERCOT queue, 14 active totaling 3,401.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityDove Wing Energy Center, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Screening study complete2024-03-19

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first