WA Parish Bus # substation interconnection queue

2 active projects totalling 308.4 MW in the ERCOT queue.

2active projects
308.4active MW
2total filed
Queue IDProjectkVMWResourceStatus
24INR0405 Crowned Heron BESS 345 154.2 Battery SS Completed, FIS Completed, IA
24INR0493 Crowned Heron BESS 2 345 154.2 Battery SS Completed, FIS Completed, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.