WA Parish
Named in 7 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of October 1, 2016.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345kV WA Parish substation” — project 76624, as the utility reported it
No HIFLD substation record has this name in this county (a record of the same name exists in another county).
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| WA Parish 345kV 80kA Fault Upgrade Upgrade WA Parish 345kV [44000] fault duty to 80KA ERCOT project 109635A |
CNP Tier 4 |
Planned Future tab |
345 | May 2030 | WA Parish Harris County |
WA Parish |
| WA Parish 345kV 80kA Fault Upgrade Upgrade WA Parish 345kV [44005] fault duty to 80KA ERCOT project 109635B |
CNP Tier 4 |
Planned Future tab |
345 | May 2030 | WA Parish Harris County |
WA Parish |
| Install new Bypass BESS II generator storage and connect to WA Parish 345kV North. Utilize same generator lead as Bypass BESS. ERCOT project 109638 |
CNP Tier 4 |
Planned Future tab |
345 | Dec 2027 | WA Parish Harris County |
WA Parish |
| WA Parish 345kV Substation Expansion for Crowned Heron Storage (24INR0405) Expand 345kV WA Parish substation for Crowned Heron Storage (24INR0405) ERCOT project 76624 |
CNP Tier 4 |
In-Service Completed tab |
345 | Oct 2025 actual 2025-12 |
WA Parish to HERON Harris County |
WA Parish, HERON |
| WA Parish 345kV Substation Expansion for Bypass Storage (23INR0336) Expand 345kV WA Parish substation for Bypass Storage (23INR0336) ERCOT project 78471 |
CNP Tier 4 |
In-Service Completed tab |
345 | Nov 2025 actual 2025-10 |
WA Parish to BYPASS Harris County |
WA Parish, BYPASS |
| Facility Ratings Methodology (FRM) Upgrades Upgrade Bellaire to WAP Ckt.50A to increase thermal limits as part of FRM upgrades ERCOT project 90232D |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Aug 2026 | Bellaire to WA Parish Harris County |
Bellaire, WA Parish |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Ckt.72A Jeanetta to WA Parish to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453K |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Dec 2026 | Jeanetta to WA Parish Harris County |
Jeanetta, WA Parish |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 90232D | Projected in-service date | Jul 2026 → Aug 2026 |
| July 13, 2026 | 90232D | Projected in-service date | Jun 2026 → Jul 2026 |
| July 13, 2026 | 109635A | First listed | on the Future tab |
| July 13, 2026 | 109635B | First listed | on the Future tab |
| July 13, 2026 | 109638 | First listed | on the Future tab |
| July 13, 2026 | 90232D | Projected in-service date | Mar 2026 → Jun 2026 |
| July 13, 2026 | 99453K | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2026 | 90232D | Projected in-service date | Jan 2026 → Mar 2026 |
| February 1, 2026 | 76624 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 76624 | Status as reported | Planned → In-Service |
| February 1, 2026 | 78471 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 78471 | Status as reported | Planned → In-Service |
| February 1, 2026 | 90232D | Projected in-service date | Sep 2025 → Jan 2026 |
| February 1, 2026 | 99453K | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 76624 | Projected in-service date | Sep 2025 → Oct 2025 |
| October 1, 2025 | 78471 | Projected in-service date | Dec 2025 → Nov 2025 |
| October 1, 2025 | 90232D | Projected in-service date | Jul 2025 → Sep 2025 |
| October 1, 2025 | 99453K | First listed | on the Future tab |
| June 1, 2025 | 76624 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 76624 | Projected in-service date | Aug 2025 → Sep 2025 |
| June 1, 2025 | 78471 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 78471 | Projected in-service date | Nov 2025 → Dec 2025 |
| June 1, 2025 | 90232D | Moved between tabs | Future → Current-year planned |
| February 1, 2025 | 90232D | First listed | on the Future tab |
| October 1, 2024 | 78471 | Projected in-service date | Sep 2025 → Nov 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.