Substation Scout

WA Parish

Named in 7 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of October 1, 2016.

Harriscounty as printed
345kV
CNPutility
7projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345kV WA Parish substation” — project 76624, as the utility reported it

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
WA Parish 345kV 80kA Fault Upgrade
Upgrade WA Parish 345kV [44000] fault duty to 80KA
ERCOT project 109635A
CNP
Tier 4
Planned
Future tab
345 May 2030 WA Parish
Harris County
WA Parish
WA Parish 345kV 80kA Fault Upgrade
Upgrade WA Parish 345kV [44005] fault duty to 80KA
ERCOT project 109635B
CNP
Tier 4
Planned
Future tab
345 May 2030 WA Parish
Harris County
WA Parish
Install new Bypass BESS II generator storage and connect to WA Parish 345kV North. Utilize same generator lead as Bypass BESS.
ERCOT project 109638
CNP
Tier 4
Planned
Future tab
345 Dec 2027 WA Parish
Harris County
WA Parish
WA Parish 345kV Substation Expansion for Crowned Heron Storage (24INR0405)
Expand 345kV WA Parish substation for Crowned Heron Storage (24INR0405)
ERCOT project 76624
CNP
Tier 4
In-Service
Completed tab
345 Oct 2025
actual 2025-12
WA Parish to HERON
Harris County
WA Parish, HERON
WA Parish 345kV Substation Expansion for Bypass Storage (23INR0336)
Expand 345kV WA Parish substation for Bypass Storage (23INR0336)
ERCOT project 78471
CNP
Tier 4
In-Service
Completed tab
345 Nov 2025
actual 2025-10
WA Parish to BYPASS
Harris County
WA Parish, BYPASS
Facility Ratings Methodology (FRM) Upgrades
Upgrade Bellaire to WAP Ckt.50A to increase thermal limits as part of FRM upgrades
ERCOT project 90232D
CNP
Tier 4
Planned
Current-year planned tab
345 Aug 2026 Bellaire to WA Parish
Harris County
Bellaire, WA Parish
Facility Ratings Methodology Phase 2 (FRM2) Upgrades
Upgrade Ckt.72A Jeanetta to WA Parish to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99453K
CNP
Tier 4
Planned
Current-year planned tab
345 Dec 2026 Jeanetta to WA Parish
Harris County
Jeanetta, WA Parish

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690232DProjected in-service dateJul 2026 → Aug 2026
July 13, 202690232DProjected in-service dateJun 2026 → Jul 2026
July 13, 2026109635AFirst listedon the Future tab
July 13, 2026109635BFirst listedon the Future tab
July 13, 2026109638First listedon the Future tab
July 13, 202690232DProjected in-service dateMar 2026 → Jun 2026
July 13, 202699453KProjected in-service dateMay 2026 → Dec 2026
June 1, 202690232DProjected in-service dateJan 2026 → Mar 2026
February 1, 202676624Moved between tabsCurrent-year planned → Completed
February 1, 202676624Status as reportedPlanned → In-Service
February 1, 202678471Moved between tabsCurrent-year planned → Completed
February 1, 202678471Status as reportedPlanned → In-Service
February 1, 202690232DProjected in-service dateSep 2025 → Jan 2026
February 1, 202699453KMoved between tabsFuture → Current-year planned
October 1, 202576624Projected in-service dateSep 2025 → Oct 2025
October 1, 202578471Projected in-service dateDec 2025 → Nov 2025
October 1, 202590232DProjected in-service dateJul 2025 → Sep 2025
October 1, 202599453KFirst listedon the Future tab
June 1, 202576624Moved between tabsFuture → Current-year planned
June 1, 202576624Projected in-service dateAug 2025 → Sep 2025
June 1, 202578471Moved between tabsFuture → Current-year planned
June 1, 202578471Projected in-service dateNov 2025 → Dec 2025
June 1, 202590232DMoved between tabsFuture → Current-year planned
February 1, 202590232DFirst listedon the Future tab
October 1, 202478471Projected in-service dateSep 2025 → Nov 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.