Substation Scout

Crowned Heron BESS

ERCOT queue ID 24INR0405

Queue ID24INR0405
Project nameCrowned Heron BESS
Status (as published)SS Completed, FIS Completed, IA
SubstationWA Parish Bus #
Point of interconnectionWA Parish 345 kV Bus #44000
CountyFort Bend
StateTX
Voltage345 kV
Capacity154.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-10-02
Source datasetlarge

Additional filed fields

Interconnecting EntityRWE Renewables
Cdr ZoneHOUSTON
Fuel CodeOTH
Technology CodeBA
Ia Signed45103
Screening Study Complete44848
Fis Approved45063
Air PermitNot Required