Fort Bend, TX interconnection queue

11 active projects totalling 2,007.9 MW in the ERCOT queue, plus 3 with terminal status (shown greyed).

11active projects
2,007.9active MW
14total filed
Queue IDProjectkVMWResourceStatus
26INR0375 Avalon BESS 345 522.1 Battery SS Completed, FIS Completed, IA
27INR0142 UNICORN BESS 138 279 Battery SS Completed, FIS Started, No IA
26INR0201 Rock Rose BESS 345 208.5 Battery SS Completed, FIS Completed, IA
26INR0525 Bypass BESS II 345 205.9 Battery SS Completed, FIS Started, No IA
25INR0372 Elan BESS 138 202.7 Battery SS Completed, FIS Completed, No IA
22INR0266 Creekfield Solar n/r 161.3 Solar Inactive
24INR0405 Crowned Heron BESS 345 154.2 Battery SS Completed, FIS Completed, IA
24INR0493 Crowned Heron BESS 2 345 154.2 Battery SS Completed, FIS Completed, IA
27INR0627 Redbird BESS 345 100 Battery SS Started, FIS Started, No IA
29INR0145 Elysium Energy Center BESS 138 100 Battery SS Completed, FIS Started, No IA
25INR0242 Pato Blanco Storage 138 71.3 Battery SS Completed, FIS Completed, No IA
22INR0379 Creekfield Storage n/r 69 Battery Inactive
22INR0548 Fighting Jays Battery n/r 53.2 Battery Inactive
23INR0556 IEP Orchard BESS 138 10 Battery In Queue

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.