tap STP to Hillje Ckt 64 substation interconnection queue

2 active projects totalling 360 MW in the ERCOT queue.

2active projects
360active MW
2total filed
Queue IDProjectkVMWResourceStatus
22INR0244 Razorbill Solar 345 240 Solar SS Completed, FIS Started, No IA
22INR0382 Razorbill Storage 345 120 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.