Tap 445 Yates - 444 Covington substation interconnection queue
2 active projects totaling 276 MW in the ERCOT queue.
2 ERCOT queue filings name Tap 445 Yates - 444 Covington as the point of interconnection, all in Hill County, TX.
Target commercial operation dates as filed run from May 2028 to Dec 2028 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: High Noon Solar Project, LLC (2 filings).
2active projects
276active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 24INR0124 | High Noon Solar | 138 | 182 | Solar | SS Completed, FIS Started, IA | Dec 2028 |
| 24INR0126 | High Noon Storage | 138 | 94 | Battery | SS Completed, FIS Started, IA | May 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Hill County, TX
- Sam Switch Bus: 2 active, 1,048.8 MW of 2 filed
- tap Venus - Sam Sw: 2 active, 404.7 MW of 2 filed
- Liberty Station: 2 active, 203.5 MW of 2 filed
- Tap Ash Creek Switch (Bus #) – Revolution Switch (Bus #): 2 active, 164.1 MW of 2 filed