Substation Scout

Tap 445 Yates - 444 Covington substation interconnection queue

2 active projects totalling 276 MW in the ERCOT queue.

2active projects
276active MW
2total filed
Queue IDProjectkVMWResourceStatus
24INR0124 High Noon Solar 138 182 Solar SS Completed, FIS Started, IA
24INR0126 High Noon Storage 138 94 Battery SS Completed, FIS Started, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.