Tap Ash Creek Switch (Bus #) – Revolution Switch (Bus #) substation interconnection queue
2 active projects totaling 164.1 MW in the ERCOT queue.
2 ERCOT queue filings name Tap Ash Creek Switch (Bus #) – Revolution Switch (Bus #) as the point of interconnection, all in Hill County, TX.
Target commercial operation date as filed: Apr 2030 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Abei Energy Green XI LLC (2 filings).
2active projects
164.1active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 26INR0402 | HILLBORO BESS | 138 | 130.9 | Battery | SS Completed, FIS Started, No IA | Apr 2030 |
| 27INR0312 | HILLBORO WIND | 138 | 33.2 | Wind | SS Completed, FIS Started, No IA | Apr 2030 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Hill County, TX
- Sam Switch Bus: 2 active, 1,048.8 MW of 2 filed
- tap Venus - Sam Sw: 2 active, 404.7 MW of 2 filed
- Tap 445 Yates - 444 Covington: 2 active, 276 MW of 2 filed
- Liberty Station: 2 active, 203.5 MW of 2 filed