Substation Scout

Sam Switch Bus substation interconnection queue

2 active projects totaling 1,048.8 MW in the ERCOT queue.

2 ERCOT queue filings name Sam Switch Bus as the point of interconnection, all in Hill County, TX.

Target commercial operation date as filed: Dec 2028 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Seven Angels Infrastructure LLC (2 filings).

2active projects
1,048.8active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
28INR0472 Seven Angels Energy Storage I 345 524.4 Battery SS Completed, FIS Started, No IA Dec 2028
28INR0473 Seven Angels Energy Storage II 345 524.4 Battery SS Completed, FIS Started, No IA Dec 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Tracked changes at this substation

2 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-11-0928INR0472Capacity revised+10.4 SS Completed, FIS Started, No IA → SS Completed, FIS Started, No IA
2026-11-0928INR0473Capacity revised+10.4 SS Completed, FIS Started, No IA → SS Completed, FIS Started, No IA

Other ERCOT queue substations in Hill County, TX