Sam Switch Bus substation interconnection queue
2 active projects totaling 1,048.8 MW in the ERCOT queue.
2 ERCOT queue filings name Sam Switch Bus as the point of interconnection, all in Hill County, TX.
Target commercial operation date as filed: Dec 2028 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Seven Angels Infrastructure LLC (2 filings).
2active projects
1,048.8active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 28INR0472 | Seven Angels Energy Storage I | 345 | 524.4 | Battery | SS Completed, FIS Started, No IA | Dec 2028 |
| 28INR0473 | Seven Angels Energy Storage II | 345 | 524.4 | Battery | SS Completed, FIS Started, No IA | Dec 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
2 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-11-09 | 28INR0472 | Capacity revised | +10.4 | SS Completed, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-11-09 | 28INR0473 | Capacity revised | +10.4 | SS Completed, FIS Started, No IA → SS Completed, FIS Started, No IA |
Other ERCOT queue substations in Hill County, TX
- tap Venus - Sam Sw: 2 active, 404.7 MW of 2 filed
- Tap 445 Yates - 444 Covington: 2 active, 276 MW of 2 filed
- Liberty Station: 2 active, 203.5 MW of 2 filed
- Tap Ash Creek Switch (Bus #) – Revolution Switch (Bus #): 2 active, 164.1 MW of 2 filed