Sweetwater East Switch substation interconnection queue

2 active projects totaling 1,288 MW in the ERCOT queue.

2 ERCOT queue filings name Sweetwater East Switch as the point of interconnection, all in Nolan County, TX.

Target commercial operation date as filed: Dec 2027 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Trailblazer Infrastructure LLC (2 filings).

2active projects
1,288active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
27INR0575 Trailblazer Natural Gas Generation Plant 345 1,026 Gas SS Completed, FIS Started, No IA Dec 2027
27INR0576 Trailblazer BESS 345 262 Battery SS Completed, FIS Started, No IA Dec 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Tracked changes at this substation

1 change to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-09-0727INR0575Status changen/a SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA

Other ERCOT queue substations in Nolan County, TX

All 18 ERCOT queue filings in Nolan County, TX.