Sweetwater East Switch substation interconnection queue

2 active projects totalling 1,288 MW in the ERCOT queue.

2active projects
1,288active MW
2total filed
Queue IDProjectkVMWResourceStatus
27INR0575 Trailblazer Natural Gas Generation Plant 345 1,026 Gas SS Started, FIS Started, No IA
27INR0576 Trailblazer BESS 345 262 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.