Bitter Creek substation interconnection queue
3 active projects totalling 192.7 MW in the ERCOT queue.
3active projects
192.7active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 18INR0031 | Maryneal Wind | 345 | 182.4 | Wind | SS Completed, FIS Completed, IA |
| 17INR0068 | Sweetwater 2 repower | 345 | 7.3 | Wind | SS Completed, FIS Completed, IA |
| 18INR0073 | Sweetwater 1 repower | 345 | 3 | Wind | SS Completed, FIS Completed, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.