Bitter Creek substation interconnection queue

3 active projects totalling 192.7 MW in the ERCOT queue.

3active projects
192.7active MW
3total filed
Queue IDProjectkVMWResourceStatus
18INR0031 Maryneal Wind 345 182.4 Wind SS Completed, FIS Completed, IA
17INR0068 Sweetwater 2 repower 345 7.3 Wind SS Completed, FIS Completed, IA
18INR0073 Sweetwater 1 repower 345 3 Wind SS Completed, FIS Completed, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.