Lost Pines Power Park
ERCOT queue ID 30INR0052
| Queue ID | 30INR0052 |
|---|---|
| Project name | Lost Pines Power Park |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | (#) LOST PINES |
| Point of interconnection | (#170174) LOST PINES 345 kV |
| County | Bastrop |
| State | TX |
| Voltage | 345 kV |
| Capacity | 880 MW |
| Resource (as published) | GAS/CC |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2033-06-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | LCRA |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | GAS |
| Technology Code | CC |
| Ia Signed | 46017 |
| Screening Study Complete | 45917 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.