Substation Scout

Taylor, TX interconnection queue

15 active projects totalling 3,534.7 MW in the ERCOT queue.

15active projects
3,534.7active MW
15total filed
Queue IDProjectkVMWResourceStatus
26INR0701 Key City Solar SLF n/r 989.1 Solar SS Completed, FIS Started, No IA
27INR0503 Dog Star Solar I 345 499 Solar SS Completed, FIS Started, No IA
27INR0504 Dog Star Solar II 345 499 Solar SS Completed, FIS Started, No IA
24INR0341 Forts Trail BESS 345 208.8 Battery SS Completed, FIS Started, No IA
24INR0488 Forts Trail BESS 2 345 205.5 Battery SS Completed, FIS Started, No IA
26INR0618 Taylor County Paul Storage 138 204.9 Battery SS Completed, FIS Completed, No IA
24INR0308 Forts Trail Solar 345 200.8 Solar SS Completed, FIS Started, No IA
26INR0626 Buffalo Gap 3 Wind Repower 138 168.5 Wind SS Completed, FIS Completed, IA
28INR0156 Chimney Rock BESS 138 156 Battery SS Completed, FIS Started, No IA
28INR0254 Summerhill BESS 138 143 Battery SS Completed, FIS Started, No IA
26INR0622 Buffalo Gap 1 Wind Repower 138 120.2 Wind SS Completed, FIS Completed, IA
28INR0293 Dart Energy Storage A1 138 50 Battery SS Completed, FIS Started, No IA
17INR0052 Horse13 CallD repower 138 44 Wind SS Completed, FIS Completed, IA
17INR0053 HHGT repower Horse13+CallD 345 44 Wind SS Completed, FIS Completed, IA
26INR0700 Key City Battery Storage SLF n/r 1.9 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.