Chimney Rock BESS
ERCOT queue ID 28INR0156
Chimney Rock BESS (28INR0156) is listed in the ERCOT interconnection queue as a 156 MW battery project in Taylor County, TX. The filing names Tap MOORE - BUTMAN as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 10, 2028. It records the screening study as complete on May 12, 2025.
| Queue ID | 28INR0156 |
|---|---|
| Project name | Chimney Rock BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap MOORE - BUTMAN |
| Point of interconnection | Tap 138kV 76317 MOORE - 76318 BUTMAN |
| County | Taylor |
| State | TX |
| Voltage | 138 kV |
| Capacity | 156 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-04-10 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Taylor, TX: 15 requests in the ERCOT queue, 13 active totaling 3,341.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Taylor ESS, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2025-05-12 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.