Concho, TX interconnection queue

6 active projects totalling 1,510.4 MW in the ERCOT queue, plus 3 with terminal status (shown greyed).

6active projects
1,510.4active MW
9total filed
Queue IDProjectkVMWResourceStatus
26INR0255 Operation Sunshine n/r 603.2 Solar Inactive
26INR0357 Operation Sunshine Storage n/r 409.8 Battery Inactive
27INR0108 Paint Rock Wind n/r 379.2 Wind SS Completed, FIS Started, No IA
25INR0225 Lucy Solar 345 352.2 Solar SS Completed, FIS Completed, IA
29INR0139 Trail Ranch Solar 1 345 302.2 Solar SS Completed, FIS Started, No IA
25INR0174 Concho Pearl Solar 345 171.9 Solar SS Completed, FIS Started, IA
25INR0175 Concho Pearl Storage 345 162.4 Battery SS Completed, FIS Started, IA
28INR0358 Cherry Sage Solar 1 SLF 138 142.5 Solar SS Completed, FIS Started, No IA
25INR0459 Old Sorrell Energy Storage n/r 43.1 Battery Inactive

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.