Substation Scout

Bell, TX interconnection queue

13 active projects totalling 3,097.7 MW in the ERCOT queue.

13active projects
3,097.7active MW
13total filed
Queue IDProjectkVMWResourceStatus
29INR0206 Riviera Gas 345 636.9 Gas SS Completed, FIS Started, No IA
26INR0465 Lavita BESS 345 606 Battery SS Completed, FIS Started, No IA
23INR0070 Chillingham Solar 345 352.4 Solar SS Completed, FIS Completed, IA
26INR0615 Bell County Morgan Storage 138 256.3 Battery SS Completed, FIS Started, No IA
26INR0614 Bell County Leifester Storage 138 204.9 Battery SS Completed, FIS Started, No IA
23INR0249 Limewood Solar 138 204.6 Solar SS Completed, FIS Completed, IA
25INR0100 Goldeneye BESS 138 201.6 Battery SS Completed, FIS Completed, IA
25INR0281 Cosper Solar 138 148.2 Solar SS Completed, FIS Completed, IA
23INR0469 Big Elm Storage 345 120 Battery SS Completed, FIS Completed, IA
25INR0337 Butcherbird Solar 138 116 Solar SS Completed, FIS Completed, No IA
24INR0365 Hermes Storage 345 100.4 Battery SS Completed, FIS Completed, IA
23INR0344 Hermes Solar 345 100.4 Solar SS Completed, FIS Completed, IA
23INR0248 Limewood Storage 138 50 Battery SS Completed, FIS Started, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.