Substation Scout

Butcherbird Solar

ERCOT queue ID 25INR0337

Queue ID25INR0337
Project nameButcherbird Solar
Status (as published)SS Completed, FIS Completed, No IA
SubstationTap - Bell County #133 to Bartlett Switch #114
Point of interconnectionTap 138 kV - Bell County #133 to Bartlett Switch #114
CountyBell
StateTX
Voltage138 kV
Capacity116 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-01-31
Source datasetlarge

Additional filed fields

Interconnecting EntityButcherbird Solar, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45366
Fis Approved45993
Air PermitNot Required
Water AvailabilityNot Required