Goldeneye BESS

ERCOT queue ID 25INR0100

Queue ID25INR0100
Project nameGoldeneye BESS
Status (as published)SS Completed, FIS Completed, IA
SubstationKILLEEN Switch
Point of interconnection3423 KILLEEN Switch 138 KV
CountyBell
StateTX
Voltage138 kV
Capacity201.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-05-15
Source datasetlarge

Additional filed fields

Interconnecting EntityBlack Mountain Energy Storage II
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Ia Signed45348
Screening Study Complete44810
Fis Approved45156
Air PermitNot Required
Water Availability45932

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.