Lavita BESS
ERCOT queue ID 26INR0465
| Queue ID | 26INR0465 |
|---|---|
| Project name | Lavita BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Temple Pecan Creek () - Temple Switch () ckt 2 |
| Point of interconnection | Tap 345kV Temple Pecan Creek (3412) - Temple Switch (3414) 345kV ckt 2 |
| County | Bell |
| State | TX |
| Voltage | 345 kV |
| Capacity | 606 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2028-07-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Lavita BESS, LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45708 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.