Atascosa, TX interconnection queue

14 active projects totalling 1,675.5 MW in the ERCOT queue.

14active projects
1,675.5active MW
14total filed
Queue IDProjectkVMWResourceStatus
27INR0396 Bluewind BESS 138 246.5 Battery SS Completed, FIS Started, No IA
28INR0343 Amphion Solar Phase 2 345 205.9 Solar SS Completed, FIS Started, No IA
29INR0214 Amphion Storage 345 200 Battery SS Completed, FIS Started, No IA
29INR0050 Amphion Solar Phase 1 345 180.6 Solar SS Completed, FIS Started, No IA
26INR0654 Great Hambino BESS 138 123 Battery SS Completed, FIS Started, No IA
21INR0391 Grandslam Solar 138 121.9 Solar SS Completed, FIS Started, IA
28INR0344 Amphion Solar Phase 3 345 115.4 Solar SS Completed, FIS Started, No IA
25INR0082 Reis Solar 138 105.5 Solar SS Completed, FIS Started, No IA
27INR0305 Kurtz Solar SLF 69 101.9 Solar SS Completed, FIS Started, No IA
28INR0208 Strawberry Dunes Solar SLF 138 101.1 Solar SS Completed, FIS Started, No IA
23INR0200 Paradiso BESS 138 100.9 Battery SS Completed, FIS Started, IA
28INR0463 Mutz Solar 69 72.8 Solar SS Completed, FIS Started, No IA
27INR0306 Kurtz Storage SLF 69 0 Battery SS Completed, FIS Started, No IA
28INR0209 Strawberry Dunes BESS SLF 138 0 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.