Substation Scout

Strawberry Dunes BESS SLF

ERCOT queue ID 28INR0209

Queue ID28INR0209
Project nameStrawberry Dunes BESS SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTap ROSSVILLESB8 () to OAKSSW8 ()
Point of interconnectionTap 138kV ROSSVILLESB8 (5718) to OAKSSW8 (5713)
CountyAtascosa
StateTX
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-06-30
Source datasetlarge

Additional filed fields

Interconnecting EntityStrawberry Dunes LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45789

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.