Substation Scout

Amphion Solar Phase 2

ERCOT queue ID 28INR0343

Queue ID28INR0343
Project nameAmphion Solar Phase 2
Status (as published)SS Completed, FIS Started, No IA
SubstationTAP (#) Fowlerton - (#) SAN MIGUEL LINE Ckt-2
Point of interconnectionTAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2
CountyAtascosa
StateTX
Voltage345 kV
Capacity205.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-05-15
Source datasetlarge

Additional filed fields

Interconnecting EntityAmphion Solar, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45857
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.