Substation Scout

Vauxhall

Named in 1 PJM planning document for 1 project, on March 13, 2025.

Not stateddescribed as
PSEGzone
69kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Kenilworth Data Center, NJ
PSEG-2024-0007
Conceptual $66.8M 06/01/2029 60 MW 2025-03-13
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 06/01/2029 → 06/2029 2025-03-13 Not reported
In-service date 06/2026 → 06/01/2029 2024-12-12 2025-03-13
Status conceptual (Conceptual) → engineering (Engineering and Planning) 2025-03-13 Not reported
Substations named GALLOPING HILL; ROSELLE; SPRINGFIELD ROAD; STANLEY TERRACE; VAUXHALL → GALLOPING HILL; ROSELLE; STANLEY TERRACE 2025-03-13 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2025-03-13 SRRTEP Mid-Atlantic
Item 02 - PSEG Supplemental Projects p. 4
Kenilworth Data Center, NJ No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this