Substation Scout

Springfield

Named in 1 PJM planning document for 1 project, on August 13, 2026.

Not stateddescribed as
PPLzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Milford Tap
PPL-2026-0032
Conceptual $1 M 11/30/2030 Not printed 2026-08-13
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named MILFORD → HOSENSACK; MILFORD; SPRINGFIELD 2026-05-14 2026-08-13

Every mention

DateDocumentProjectWhat the document says about it
2026-08-13 SRRTEP Mid-Atlantic
Item 05 - PPL Supplemental Projects p. 12
Milford Tap No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this