Lakeview

Named in 2 PJM planning documents for 2 projects, from December 3, 2024 to January 7, 2025.

Existingdescribed as
PJM system-widezone
230kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Recommended Solution: 2024-W1-24
b4000.300
Not printed $672.43 M 6/1/2029 Not printed 2025-01-07
TEAC
2024W1 – Regional Cluster Preferred Solution: 2024-W1-24
2024-W1-24
Not printed $672.43 M 6/1/2029 Not printed 2024-12-03
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-01-07 TEAC
Item 12 - Reliability Analysis Update p. 67
Recommended Solution: 2024-W1-24 “Terminal equipment upgrades at Thelma & Lakeview”
230kV
2024-12-03 TEAC
Item 11 - Reliability Analysis Update p. 80
2024W1 – Regional Cluster Preferred Solution: 2024-W1-24 “Terminal equipment upgrades at Thelma & Lakeview”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.