Substation Scout

Chilcott

Named in 2 PJM planning documents for 1 project, from August 4, 2026 to October 6, 2026.

Not stateddescribed as
JCPLzone
34.5 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Greystone 230-34.5 kV Substation, NJ
JCPL-2026-045
Conceptual $9.71 M 12/15/2029 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named CHILCOTT; DENVILLE; FOLL HILL; GREYSTONE; WEST DENVILLE → CHILCOTT; DENVILLE; FOLL HILL; GREYSTONE; MONTVILLE; MORRISTOWN; ROCKAWAY; WEST DENVILLE 2026-08-04 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 08 - JCPL Supplemental Projects - Presentation p. 4
Greystone 230-34.5 kV Substation, NJ No role wording
34.5 kV
2026-08-04 TEAC
Item 05 - JCPL Supplemental Projects p. 5
Greystone 230-34.5 kV Substation, NJ No role wording
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.