Morristown Tap
Named in 3 PJM planning documents for 1 project, from March 13, 2025 to October 8, 2025.
Existingdescribed as
JCPLzone
34.5 kVkV as printed
3mentions
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ JCPL-2019-024 · s3609.1 |
Not printed | $20.1 M | 06/11/2027 | Not printed | 2025-10-08 TEAC |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| Cost estimate | $40.2 M → $20.1 M | 2025-03-13 | 2025-10-08 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Mid-Atlantic JCPL local plan submission for 2025 RTEP p. 3 |
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ | “Replace three existing line switches with 1200A MOAB switches at Morristown Tap” |
| 2025-10-08 | TEAC Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 3 |
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ | “Replace three existing line switches with 1200A MOAB switches at Morristown Tap” 34.5 kV |
| 2025-03-13 | SRRTEP Mid-Atlantic Item 05 - JCPL Supplemental Projects p. 8 |
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ | “Replace three existing line switches with 1200A MOAB switches at Morristown Tap” 34.5 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.