Morris Plains Tap

Named in 3 PJM planning documents for 1 project, from March 13, 2025 to October 8, 2025.

Not stateddescribed as
JCPLzone
34. 5 kV, 34.5 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ
JCPL-2019-024 · s3609.1
Not printed $20.1 M 06/11/2027 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $40.2 M → $20.1 M 2025-03-13 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2025 RTEP p. 2
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ No role wording
2025-10-08 TEAC
Informational Only - JCPL Local Plan Submission of the Supplemental Projects for 2025 p. 2
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ No role wording
34. 5 kV
2025-03-13 SRRTEP Mid-Atlantic
Item 05 - JCPL Supplemental Projects p. 8
JCPL Transmission Zone M-3 Process Whippany, NJ/Montville, NJ/Greystone, NJ No role wording
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.