Substation Scout

Gillette

Named in 7 PJM planning documents for 5 projects, from October 8, 2024 to October 16, 2026.

Existingdescribed as
JCPLzone
230 kV, 34.5 kVkV as printed
8mentions

Also printed as: Gillette Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Middlesex 230 kV Switching Station
s3261.1
Not printed $8.85M FirstEnergy, $9.04M PSE&G 12/31/2027 Not printed 2025-01-07
TEAC
Gillette – Green Village 34.5 kV Lines
JCPL-2019-026 · s3232.1
Not printed $ 24.2 M 02/23/2024 Not printed 2024-10-08
TEAC
Middlesex 230 kV Switching Station
JCPL-2023-062 · s3261.1
Not printed $8.85M 6/1/2026 Not printed 2026-09-08*
SRRTEP Mid-Atlantic
Bernardsville - Gillette 34.5 kV B730 Line
JCPL-2024-011 · s3970.1
Not printed $20.51M 06/30/2028 Not printed 2026-10-06
TEAC
New Providence Substation 34.5 kV Breaker Replacement
JCPL-2025-009
Conceptual $13.03 M 05/31/2030 Not printed 2026-10-16
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named MIDDLESEX → BRIDGEWATER; GILLETTE; LAKE NELSON; MIDDLESEX 2024-10-08 Not reported
Substations named BERNARDSVILLE; GILLETTE; LYONS; MARTINSVILLE; STIRLING → GILLETTE; STIRLING 2026-10-06 Not reported
Substations named BERNARDSVILLE; GILLETTE; LYONS; MARTINSVILLE; STIRLING; STIRLING TAP → BERNARDSVILLE; GILLETTE; LYONS; MARTINSVILLE; STIRLING 2026-07-17 2026-10-06
Substations named AIR REDUCTION; CSC H TAP; NEW PROVIDENCE → AIR REDUCTION; GILLETTE; MURRAY HILL; NEW PROVIDENCE 2025-12-11 2026-10-16

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Mid-Atlantic
Item 06 - JCPL Supplemental Projects Presentation p. 12
New Providence Substation 34.5 kV Breaker Replacement No role wording
34.5 kV
2026-10-06 TEAC
Informational Only - JCPL Local Plan Submission of Supplemental Projects for 2026 p. 42
Bernardsville - Gillette 34.5 kV B730 Line “At Gillette Substation: Upgrade relay settings”
34.5 kV
2026-10-01* SRRTEP Mid-Atlantic
JCPL local plan submission for 2026 RTEP p. 42
Bernardsville - Gillette 34.5 kV B730 Line “At Gillette Substation: Upgrade relay settings.”
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 37
Middlesex 230 kV Switching Station No role wording
230 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 5
Gillette – Green Village 34.5 kV Lines “Gillette Substation: Replace line relaying”
34.5 kV
2026-07-17 SRRTEP Mid-Atlantic
Item 02 - JCPL Supplemental Projects p. 7
Bernardsville - Gillette 34.5 kV B730 Line “At Gillette Substation: Upgrade relay settings.”
34.5 kV
2025-01-07 TEAC
Item 06 - JCPL Supplemental Projects p. 3
Middlesex 230 kV Switching Station No role wording
230 kV
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 5
Gillette – Green Village 34.5 kV Lines “Gillette Substation: Replace line relaying, limiting substation conductor”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.