Substation Scout

Oasis

Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
1projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
CC: NORTH SPA 230kV (NETWORK IMPROVEMENTS)
This project includes the following scope of work: Build a new 230kV switching station north of Oasis with 4 - breakers. Loop in the East Social Circle - Oasis (White) 230kV line. Build new Alcovy Trestle 230kV switching Station. Build new 7 miles, 230kV line from North Spa to Alcovy Trestle with (2) 200C 1351 ACSS. Build new 6 miles, 230kV line from Morning Hornet to Alcovy Trestle with (2) 200C 1351 ACSS. Build (2)…
TEAMS 21093 · plan p.144 · zone 214
GPC In the plan
p.11
Jun 1, 2027 Advanced from 2030 to 2027 East Social Circle, Oasis

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.