Winder Primary
Named in 5 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
5projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| LAWRENCEVILLE - WINDER PRIMARY 115kV LINE REBUILD Rebuild approximately 1.2 miles of the Lawrenceville - Winder 115kV line from Johns Manville to Winder Primary with 200C 795 ACSS conductor. TEAMS 10143 · plan p.259 · zone 202 |
GPC | In the plan p.19 |
Jun 1, 2030 | Delayed from 2027 to 2030 | Lawrenceville, Winder, Winder Primary |
| LAWRENCEVILLE - WINDER PRIMARY 230kV LINE REBUILD Rebuild the entire Lawrenceville - Winder Primary 230kV line, approximately 19.4 miles, with 1351 ACSS Martin conductor. TEAMS 10481 · plan p.138 · zone 202 |
GPC | In the plan p.11 |
Jun 1, 2027 | No change | Lawrenceville, Winder Primary |
| WINDER PRIMARY 230kV BREAKER INSTALLATION Install a 230kV breaker at the Winder Primary Station. TEAMS 20759 · plan p.298 · zone 202 |
GPC | In the plan p.22 |
Jun 1, 2033 | No change | Winder Primary |
| GTC: CLARKSBORO - WINDER PRIMARY 230kV REBUILD Rebuild approximately 14 miles of the Clarksboro - Winder 230kV line with 200C 1351 ACSS conductor. TEAMS 20773 · plan p.205 · zone 212 |
GTC | In the plan p.16 |
Jun 1, 2029 | Advanced from 2033 to 2029 | Clarksboro, Winder, Winder Primary |
| GTC: DOYLE - WINDER PRIMARY 230kV LINE JUMPER REPLACEMENT Replace the limiting jumper with higher rated equipment at Doyle on the Doyle - Winder Primary 230kV line. TEAMS 20778 · plan p.128 · zone 212 |
GTC | In the plan p.10 |
Jun 1, 2027 | No change | Doyle, Winder Primary |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner