Substation Scout

Tomball

Named in 8 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2015.

Harriscounty as printed
138, 345kV
CNPutility
8projects listed

A HIFLD substation record has the same name and county: TOMBALL (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This models upgrades related to the Willow Phase 3 Load addition
Build a new 138 kV circuit between Tomball and T.H. Wharton using the open circuit position on the existing double circuit towers. Loop the new circuit into Willow substation creating TH Wharton to Willow to Tomball.
ERCOT project 109769A · RPG 26RPG023
CNP
Tier 3
Conceptual
Future tab
138 Jun 2028 Willow to Tomball/TH Wharton
Harris County
Willow, Tomball, TH Wharton
This models upgrades related to the Willow Phase 3 Load addition
Reconfigure 138 kV ckt.81 Tomball to Mill Creek to Pinehurst to Kluge by looping the Pinehurst to Kluge ckt.81 segment into Tomball creating the following circuit Tomball to Mill Creek to Pinehurst to Tomball.
ERCOT project 109769C · RPG 26RPG023
CNP
Tier 3
Conceptual
Future tab
138 Jun 2028 Tomball to Pinehurst
Harris County
Tomball, Pinehurst
This models upgrades related to the Willow Phase 3 Load addition
Reconfigure 138 kV ckt.81 Tomball to Mill Creek to Pinehurst to Kluge to create a new cicuit from Kluge to Tomball
ERCOT project 109769D · RPG 26RPG023
CNP
Tier 3
Conceptual
Future tab
138 Jun 2028 Kluge to Tomball
Harris County
Kluge, Tomball
Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Install 40 MVAR cap bank at Hockley substation and tapped on Ckt.66B Hockley to Stone Lake.
Partial reconductor Ckt.66B Stone Lake to Tomball. Phase One of overall approved upgrades
ERCOT project 75835A · RPG 23RPG012
CNP
Tier 3
In-Service
Completed tab
138 Aug 2025
actual 2025-07
Stone Lake to Tomball
Harris County
Stone Lake, Tomball
Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Install 40 MVAR cap bank at Hockley substation and tapped on Ckt.66B Hockley to Stone Lake.
Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Phase Three of overall approved upgrades.
ERCOT project 75835C · RPG 23RPG012
CNP
Tier 3
Planned
Future tab
138 May 2027 Stone Lake to Tomball
Harris County
Stone Lake, Tomball
Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Install 40 MVAR cap bank at Hockley substation and tapped on Ckt.66B Hockley to Stone Lake.
Upgrade equipment to increase thermal limits. Phase Two of overall approved upgrades
ERCOT project 75835D · RPG 23RPG012
CNP
Tier 3
In-Service
Completed tab
138 May 2026
actual 2025-12
Stone Lake to Tomball
Harris County
Stone Lake, Tomball
Install new Mill Creek (MLC) distribution substation with (2) 100 MVA transformers.
Install new Mill Creek (MLC) distribution substation with (2) 100 MVA transformers. Loop substation on Ckt.81G to create new Ckt.81G Pinehurst to Mill Creek to Tomball.
ERCOT project 90161A
CNP
Tier 4
Planned
Future tab
138 Dec 2027 Mill Creek to Pinehurst /Tomball
Montgomery / Harris County
Mill Creek, Pinehurst, Tomball
Facility Ratings Methodology Phase 2 (FRM2) Upgrades
Upgrade Ckt.74C Tomball to Singleton to increase thermal limits as part of FRM2 upgrades.
ERCOT project 99453T
CNP
Tier 4
Planned
Future tab
345 Oct 2029 Tomball to Singleton
Harris / Grimes County
Tomball, Singleton

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690161AProjected in-service dateOct 2027 → Dec 2027
July 13, 2026109769AFirst listedon the Future tab
July 13, 2026109769CFirst listedon the Future tab
July 13, 2026109769DFirst listedon the Future tab
July 13, 202690161AMoved between tabsCurrent-year planned → Future
July 13, 202690161AProjected in-service dateDec 2026 → Oct 2027
June 1, 202675835DMoved between tabsCurrent-year planned → Completed
February 1, 202675835AProjected in-service dateJul 2025 → Aug 2025
February 1, 202675835DMoved between tabsFuture → Current-year planned
February 1, 202675835DStatus as reportedPlanned → In-Service
February 1, 202690161AMoved between tabsFuture → Current-year planned
October 1, 202575835AMoved between tabsCurrent-year planned → Completed
October 1, 202575835AStatus as reportedPlanned → In-Service
October 1, 202575835AProjected in-service dateMay 2025 → Jul 2025
October 1, 202575835DFirst listedon the Future tab
October 1, 202590161AProjected in-service dateAug 2026 → Dec 2026
October 1, 202599453TFirst listedon the Future tab
June 1, 202575835AMoved between tabsFuture → Current-year planned
February 1, 202575835AProjected in-service dateOct 2026 → May 2025
February 1, 202575835CFirst listedon the Future tab
February 1, 202590161AFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first