Stone Lake
Named in 7 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of October 1, 2020.
Harriscounty as printed
138kV
CNPutility
7projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Prairieland 138/35kV Distribution Substation Install Prairieland (PRL) 138/35kV Distribution Substation. Loop on Ckt.66B Hockley to Stone Lake to create new Ckt.66B Hockley to Prairieland to Stone Lake. ERCOT project 102777 |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Prairieland to Hockley/Stone Lake Harris County |
Prairieland, Hockley, Stone Lake |
| Ckt.66B Stone Lake to Hockley Hardening and Waller Cap Bank Upgrade Ckt.66B Hockley to (Prairieland) to Stone Lake to increase thermal limits (Hockley equipment upgrade) ERCOT project 104643A |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Stone Lake to Hockley Harris County |
Stone Lake, Hockley |
| Ckt.66B Stone Lake to Hockley Hardening and Waller Cap Bank Rebuild and reconductor Ckt.66B Hockley to (Prairieland) to Stone Lake as a Hardening upgrade. ERCOT project 104643C |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Stone Lake to Hockley Harris County |
Stone Lake, Hockley |
| Ckt.66B Stone Lake to Hockley Hardening and Waller Cap Bank Rebuild and reconductor Ckt.66B Hockley to (Prairieland) to Stone Lake as a Hardening upgrade. ERCOT project 104643D |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Stone Lake to Hockley Harris County |
Stone Lake, Hockley |
| Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Install 40 MVAR cap bank at Hockley substation and tapped on Ckt.66B Hockley to Stone Lake. Partial reconductor Ckt.66B Stone Lake to Tomball. Phase One of overall approved upgrades ERCOT project 75835A · RPG 23RPG012 |
CNP Tier 3 |
In-Service Completed tab |
138 | Aug 2025 actual 2025-07 |
Stone Lake to Tomball Harris County |
Stone Lake, Tomball |
| Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Install 40 MVAR cap bank at Hockley substation and tapped on Ckt.66B Hockley to Stone Lake. Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Phase Three of overall approved upgrades. ERCOT project 75835C · RPG 23RPG012 |
CNP Tier 3 |
Planned Future tab |
138 | May 2027 | Stone Lake to Tomball Harris County |
Stone Lake, Tomball |
| Upgrade Ckt.66B Stone Lake to Tomball to increase thermal limits. Install 40 MVAR cap bank at Hockley substation and tapped on Ckt.66B Hockley to Stone Lake. Upgrade equipment to increase thermal limits. Phase Two of overall approved upgrades ERCOT project 75835D · RPG 23RPG012 |
CNP Tier 3 |
In-Service Completed tab |
138 | May 2026 actual 2025-12 |
Stone Lake to Tomball Harris County |
Stone Lake, Tomball |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 104643A | First listed | on the Future tab |
| June 1, 2026 | 104643C | First listed | on the Future tab |
| June 1, 2026 | 104643D | First listed | on the Future tab |
| June 1, 2026 | 75835D | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 102777 | First listed | on the Future tab |
| February 1, 2026 | 75835A | Projected in-service date | Jul 2025 → Aug 2025 |
| February 1, 2026 | 75835D | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 75835D | Status as reported | Planned → In-Service |
| October 1, 2025 | 75835A | Moved between tabs | Current-year planned → Completed |
| October 1, 2025 | 75835A | Status as reported | Planned → In-Service |
| October 1, 2025 | 75835A | Projected in-service date | May 2025 → Jul 2025 |
| October 1, 2025 | 75835D | First listed | on the Future tab |
| June 1, 2025 | 75835A | Moved between tabs | Future → Current-year planned |
| February 1, 2025 | 75835A | Projected in-service date | Oct 2026 → May 2025 |
| February 1, 2025 | 75835C | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner