Pinehurst
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2025.
No HIFLD substation record has this name in this county (a record of the same name exists in another county).
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| This models upgrades related to the Willow Phase 3 Load addition Reconfigure 138 kV ckt.81 Tomball to Mill Creek to Pinehurst to Kluge by looping the Pinehurst to Kluge ckt.81 segment into Tomball creating the following circuit Tomball to Mill Creek to Pinehurst to Tomball. ERCOT project 109769C · RPG 26RPG023 |
CNP Tier 3 |
Conceptual Future tab |
138 | Jun 2028 | Tomball to Pinehurst Harris County |
Tomball, Pinehurst |
| Install new Mill Creek (MLC) distribution substation with (2) 100 MVA transformers. Install new Mill Creek (MLC) distribution substation with (2) 100 MVA transformers. Loop substation on Ckt.81G to create new Ckt.81G Pinehurst to Mill Creek to Tomball. ERCOT project 90161A |
CNP Tier 4 |
Planned Future tab |
138 | Dec 2027 | Mill Creek to Pinehurst /Tomball Montgomery / Harris County |
Mill Creek, Pinehurst, Tomball |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 90161A | Projected in-service date | Oct 2027 → Dec 2027 |
| July 13, 2026 | 109769C | First listed | on the Future tab |
| July 13, 2026 | 90161A | Moved between tabs | Current-year planned → Future |
| July 13, 2026 | 90161A | Projected in-service date | Dec 2026 → Oct 2027 |
| February 1, 2026 | 90161A | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 90161A | Projected in-service date | Aug 2026 → Dec 2026 |
| February 1, 2025 | 90161A | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.