Jeanetta
Named in 12 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of June 1, 2016.
A HIFLD substation record has the same name and county: JEANETTA (HARRIS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| High Voltage Mitigation - WA Parish Area Install (2) 40 MVAr shunt reactors on the tertiary of Jeanetta Auto A1 ERCOT project 104744C |
CNP Tier 4 |
Planned Future tab |
345 | Dec 2027 | Jeanetta Harris County |
Jeanetta |
| High Voltage Mitigation - WA Parish Area Install (2) 40 MVAr shunt reactors on the tertiary of Jeanetta Auto A2 ERCOT project 104744D |
CNP Tier 4 |
Planned Future tab |
345 | Dec 2027 | Jeanetta Harris County |
Jeanetta |
| BP24 Sub Upgrades Upgrade Jeanetta to WA Parish Ckt.64A to increase thermal limits ERCOT project 73371F |
CNP Tier 4 |
In-Service Completed tab |
138 | Jan 2025 actual 2025-06 |
Jeanetta to WA Parish Harris / Fort Bend County |
Jeanetta, WA Parish |
| BP24 Sub Upgrades Upgrade White Oak to Jeanetta Ckt.72B to increase thermal limits ERCOT project 73371H |
CNP Tier 4 |
In-Service Completed tab |
345 | Jan 2025 actual 2025-02 |
White Oak to Jeanetta Harris County |
White Oak, Jeanetta |
| Jeanetta Auto Upgrades Replace existing 600 MVA Jeanetta Auto A1 with 800 MVA autotransformer ERCOT project 78490A · RPG 23RPG031 |
CNP Tier 3 |
In-Service Completed tab |
345 | Oct 2025 actual 2025-05 |
Jeanetta Harris County |
Jeanetta |
| Jeanetta Auto Upgrades Replace existing 600 MVA Jeanetta Auto A3 with 800 MVA autotransformer ERCOT project 78490B · RPG 23RPG031 |
CNP Tier 3 |
In-Service Completed tab |
345 | Oct 2025 actual 2025-03 |
Jeanetta Harris County |
Jeanetta |
| Upgrade Ckt 25 Jeanetta to Westwood to increase thermal limits ERCOT project 87346 |
CNP Tier 4 |
Planned Current-year planned tab |
138 | Dec 2026 actual 2026-07 |
Westwood to Jeanetta Harris County |
Westwood, Jeanetta |
| Upgrade to increase thermal limits as part of FRM upgrades Upgrade Jeanetta to WA Parish Ckt.64A to increase thermal limits as part of FRM upgrades ERCOT project 87479E |
CNP Tier 4 |
Conceptual Current-year planned tab |
345 | Jul 2025 | Jeanetta to WAP Harris / Fort Bend County |
Jeanetta, WAP |
| Upgrade to increase thermal limits as part of FRM upgrades Upgrade Bellaire to Jeanetta Ckt.64B to increase thermal limits as part of FRM upgrades ERCOT project 87479F |
CNP Tier 4 |
Conceptual Current-year planned tab |
345 | Jul 2025 | Bellaire to Jeanetta Harris County |
Bellaire, Jeanetta |
| Facility Ratings Methodology (FRM) Upgrades Upgrade Jeanetta to WA Parish Ckt.64A to increase thermal limits as part of FRM upgrades ERCOT project 90232E |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Sep 2026 | Jeanetta to WA Parish Harris / Fort Bend County |
Jeanetta, WA Parish |
| Facility Ratings Methodology (FRM) Upgrades Upgrade Bellaire to Jeanetta Ckt.64B to increase thermal limits as part of FRM upgrades ERCOT project 90232F |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Aug 2026 | Bellaire to Jeanetta Harris County |
Bellaire, Jeanetta |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Ckt.72A Jeanetta to WA Parish to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453K |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Dec 2026 | Jeanetta to WA Parish Harris County |
Jeanetta, WA Parish |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 90232E | Projected in-service date | Jul 2026 → Sep 2026 |
| October 1, 2026 | 90232F | Projected in-service date | Jul 2026 → Aug 2026 |
| July 13, 2026 | 87479E | Status as reported | Planned → Conceptual |
| July 13, 2026 | 87479F | Status as reported | Planned → Conceptual |
| July 13, 2026 | 90232E | Projected in-service date | Jun 2026 → Jul 2026 |
| July 13, 2026 | 90232F | Projected in-service date | Jun 2026 → Jul 2026 |
| July 13, 2026 | 104744C | Projected in-service date | Oct 2027 → Dec 2027 |
| July 13, 2026 | 104744D | Projected in-service date | Oct 2027 → Dec 2027 |
| July 13, 2026 | 90232E | Projected in-service date | Mar 2026 → Jun 2026 |
| July 13, 2026 | 90232F | Projected in-service date | Mar 2026 → Jun 2026 |
| July 13, 2026 | 99453K | Projected in-service date | May 2026 → Dec 2026 |
| June 1, 2026 | 104744C | First listed | on the Future tab |
| June 1, 2026 | 104744D | First listed | on the Future tab |
| June 1, 2026 | 90232E | Projected in-service date | Jan 2026 → Mar 2026 |
| June 1, 2026 | 90232F | Projected in-service date | Jan 2026 → Mar 2026 |
| February 1, 2026 | 78490A | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 78490A | Status as reported | Planned → In-Service |
| February 1, 2026 | 78490B | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 78490B | Status as reported | Planned → In-Service |
| February 1, 2026 | 87346 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 87346 | Projected in-service date | May 2026 → Dec 2026 |
| February 1, 2026 | 90232E | Projected in-service date | Sep 2025 → Jan 2026 |
| February 1, 2026 | 90232F | Projected in-service date | Sep 2025 → Jan 2026 |
| February 1, 2026 | 99453K | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 90232E | Projected in-service date | Jul 2025 → Sep 2025 |
| October 1, 2025 | 90232F | Projected in-service date | Jul 2025 → Sep 2025 |
| October 1, 2025 | 99453K | First listed | on the Future tab |
| June 1, 2025 | 73371F | Status as reported | Planned → In-Service |
| June 1, 2025 | 73371H | Status as reported | Planned → In-Service |
| June 1, 2025 | 78490A | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 78490B | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 87479E | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 87479F | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 90232E | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 90232F | Moved between tabs | Future → Current-year planned |
| February 1, 2025 | 73371F | Projected in-service date | Jun 2024 → Jan 2025 |
| February 1, 2025 | 73371H | Moved between tabs | Future → Completed |
| February 1, 2025 | 73371H | Projected in-service date | Nov 2024 → Jan 2025 |
| February 1, 2025 | 78490A | Projected in-service date | May 2025 → Oct 2025 |
| February 1, 2025 | 78490B | Projected in-service date | May 2025 → Oct 2025 |
| February 1, 2025 | 90232E | First listed | on the Future tab |
| February 1, 2025 | 90232F | First listed | on the Future tab |
| October 1, 2024 | 73371F | Projected in-service date | May 2024 → Jun 2024 |
| October 1, 2024 | 73371H | Moved between tabs | Completed → Future |
| October 1, 2024 | 73371H | Projected in-service date | May 2024 → Nov 2024 |
| October 1, 2024 | 87346 | First listed | on the Future tab |
| October 1, 2024 | 87479E | First listed | on the Future tab |
| October 1, 2024 | 87479F | First listed | on the Future tab |
| June 1, 2024 | 73371F | Moved between tabs | Future → Completed |
| June 1, 2024 | 73371H | Moved between tabs | Future → Completed |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.