Bellaire
Named in 15 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: BELLAIRE (HARRIS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Bellaire 35kV Distribution Upgrades with 3rd Transformer Reconfigure 35kV Bellaire distribution facilities. Install new 35kV Bellaire distribution TR7 with Ckt.24B service. ERCOT project 103003A |
CNP Tier 4 |
Planned Current-year planned tab |
138 | Nov 2026 | Bellaire Harris County |
Bellaire |
| Bellaire 35kV Distribution Upgrades with 3rd Transformer Reconfigure 35kV Bellaire distribution facilities. Reconfigure Bellaire 35kV distribution transformer TR6 to receive Ckt.35E service. Reconductor portions of Ckt.35E. ERCOT project 103003B |
CNP Tier 4 |
Planned Current-year planned tab |
138 | Nov 2026 | Bellaire Harris County |
Bellaire |
| Bellaire to Ulrich Hardening Rebuild/reconductor portions of Ckt.35 Bellaire to Ulrich as a Hardening upgrade. ERCOT project 103423 |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Bellaire to Ulrich Harris County |
Bellaire, Ulrich |
| Rebuild/reconductor Ckt.94C Metals Switchrack to METALS as a Hardening upgrade Rebuild/reconductor portions of Ckt.35 Bellaire to Ulrich as a Hardening upgrade. ERCOT project 103427 |
CNP Tier 4 |
Planned Current-year planned tab |
138 | Dec 2026 | Bellaire to Ulrich Harris County |
Bellaire, Ulrich |
| High Voltage Mitigation - WA Parish Area Install (2) 40 MVAr shunt reactors on the tertiary of Bellaire Auto A1 ERCOT project 104744A |
CNP Tier 4 |
Planned Future tab |
345 | Dec 2027 | Bellaire Harris County |
Bellaire |
| High Voltage Mitigation - WA Parish Area Install (2) 40 MVAr shunt reactors on the tertiary of Bellaire Auto A2 ERCOT project 104744B |
CNP Tier 4 |
Planned Future tab |
345 | Dec 2027 | Bellaire Harris County |
Bellaire |
| Removal of 140MVAr SVC and facilities from Bellaire and Crosby 138kV substations. Remove the 140MVAr SVC and facilities from Bellaire 138kV substation ERCOT project 112585A |
CNP Tier 4 |
Planned Future tab |
138 | May 2027 | Bellaire Harris County |
Bellaire |
| BP24 Sub Upgrades Upgrade Bellaire Auto A5 CTs to increase thermal limits ERCOT project 73371B |
CNP Tier 4 |
In-Service Completed tab |
138 | Jun 2026 actual 2026-06 |
Bellaire Harris County |
Bellaire |
| Britmoore to Bellaire Ckt.24B Upgrades Upgrade portions of Ckt.05E Bellaire to Sharpstown to Hillcroft to increase thermal limits. ERCOT project 78485C · RPG 23RPG025 |
CNP Tier 3 |
Planned Current-year planned tab |
138 | Dec 2026 | Bellaire to Hillcroft Harris County |
Bellaire, Hillcroft |
| Britmoore to Bellaire Ckt.24B Upgrades Upgrade Ckt.24B Bellaire to Ulrich to Hillcroft to increase thermal limits. ERCOT project 78485D · RPG 23RPG025 |
CNP Tier 3 |
Planned Current-year planned tab |
138 | Dec 2026 | Bellaire to Hillcroft Harris County |
Bellaire, Hillcroft |
| Upgrade to increase thermal limits as part of FRM upgrades Upgrade Bellaire to WAP Ckt.50A to increase thermal limits as part of FRM upgrades ERCOT project 87479D |
CNP Tier 4 |
Conceptual Current-year planned tab |
345 | Jul 2025 | Bellaire to WAP Harris / Fort Bend County |
Bellaire, WAP |
| Upgrade to increase thermal limits as part of FRM upgrades Upgrade Bellaire to Jeanetta Ckt.64B to increase thermal limits as part of FRM upgrades ERCOT project 87479F |
CNP Tier 4 |
Conceptual Current-year planned tab |
345 | Jul 2025 | Bellaire to Jeanetta Harris County |
Bellaire, Jeanetta |
| Facility Ratings Methodology (FRM) Upgrades Upgrade Bellaire to WAP Ckt.50A to increase thermal limits as part of FRM upgrades ERCOT project 90232D |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Aug 2026 | Bellaire to WA Parish Harris County |
Bellaire, WA Parish |
| Facility Ratings Methodology (FRM) Upgrades Upgrade Bellaire to Jeanetta Ckt.64B to increase thermal limits as part of FRM upgrades ERCOT project 90232F |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Aug 2026 | Bellaire to Jeanetta Harris County |
Bellaire, Jeanetta |
| Facility Ratings Methodology Phase 2 (FRM2) Upgrades Upgrade Ckt.98A Bellaire to Smithers to increase thermal limits as part of FRM2 upgrades. ERCOT project 99453J |
CNP Tier 4 |
Planned Current-year planned tab |
345 | Dec 2026 | Bellaire to Smithers Harris / Fort Bend County |
Bellaire, Smithers |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 112585A | First listed | on the Future tab |
| October 1, 2026 | 90232D | Projected in-service date | Jul 2026 → Aug 2026 |
| October 1, 2026 | 90232F | Projected in-service date | Jul 2026 → Aug 2026 |
| July 13, 2026 | 103427 | Moved between tabs | Future → Current-year planned |
| July 13, 2026 | 103427 | Projected in-service date | Dec 2028 → Dec 2026 |
| July 13, 2026 | 87479D | Status as reported | Planned → Conceptual |
| July 13, 2026 | 87479F | Status as reported | Planned → Conceptual |
| July 13, 2026 | 90232D | Projected in-service date | Jun 2026 → Jul 2026 |
| July 13, 2026 | 90232F | Projected in-service date | Jun 2026 → Jul 2026 |
| July 13, 2026 | 103003A | Projected in-service date | Oct 2026 → Nov 2026 |
| July 13, 2026 | 103003B | Projected in-service date | Oct 2026 → Nov 2026 |
| July 13, 2026 | 104744A | Projected in-service date | Oct 2027 → Dec 2027 |
| July 13, 2026 | 104744B | Projected in-service date | Oct 2027 → Dec 2027 |
| July 13, 2026 | 73371B | Moved between tabs | Current-year planned → Completed |
| July 13, 2026 | 73371B | Status as reported | Planned → In-Service |
| July 13, 2026 | 73371B | Projected in-service date | Mar 2026 → Jun 2026 |
| July 13, 2026 | 90232D | Projected in-service date | Mar 2026 → Jun 2026 |
| July 13, 2026 | 90232F | Projected in-service date | Mar 2026 → Jun 2026 |
| June 1, 2026 | 103003A | First listed | on the Current-year planned tab |
| June 1, 2026 | 103003B | First listed | on the Current-year planned tab |
| June 1, 2026 | 103423 | First listed | on the Future tab |
| June 1, 2026 | 103427 | First listed | on the Future tab |
| June 1, 2026 | 104744A | First listed | on the Future tab |
| June 1, 2026 | 104744B | First listed | on the Future tab |
| June 1, 2026 | 73371B | Projected in-service date | Jan 2026 → Mar 2026 |
| June 1, 2026 | 90232D | Projected in-service date | Jan 2026 → Mar 2026 |
| June 1, 2026 | 90232F | Projected in-service date | Jan 2026 → Mar 2026 |
| February 1, 2026 | 73371B | Projected in-service date | Nov 2025 → Jan 2026 |
| February 1, 2026 | 78485C | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 78485D | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 90232D | Projected in-service date | Sep 2025 → Jan 2026 |
| February 1, 2026 | 90232F | Projected in-service date | Sep 2025 → Jan 2026 |
| February 1, 2026 | 99453J | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 99453J | Projected in-service date | May 2026 → Dec 2026 |
| October 1, 2025 | 73371B | Projected in-service date | Oct 2025 → Nov 2025 |
| October 1, 2025 | 78485C | Projected in-service date | May 2026 → Dec 2026 |
| October 1, 2025 | 78485D | Projected in-service date | May 2026 → Dec 2026 |
| October 1, 2025 | 90232D | Projected in-service date | Jul 2025 → Sep 2025 |
| October 1, 2025 | 90232F | Projected in-service date | Jul 2025 → Sep 2025 |
| October 1, 2025 | 99453J | First listed | on the Future tab |
| June 1, 2025 | 73371B | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 87479D | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 87479F | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 90232D | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 90232F | Moved between tabs | Future → Current-year planned |
| February 1, 2025 | 73371B | Projected in-service date | Oct 2024 → Oct 2025 |
| February 1, 2025 | 78485D | Projected in-service date | May 2025 → May 2026 |
| February 1, 2025 | 90232D | First listed | on the Future tab |
| February 1, 2025 | 90232F | First listed | on the Future tab |
| October 1, 2024 | 73371B | Moved between tabs | Completed → Future |
| October 1, 2024 | 73371B | Projected in-service date | May 2024 → Oct 2024 |
| October 1, 2024 | 87479D | First listed | on the Future tab |
| October 1, 2024 | 87479F | First listed | on the Future tab |
| June 1, 2024 | 73371B | Moved between tabs | Future → Completed |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.