Substation Scout

South Creek

Named in 2 PJM planning documents for 1 project, from May 6, 2025 to October 6, 2026.

Existingdescribed as
DOMzone
115kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Supplemental Customer Load Request
DOM-2025-0020
Engineering $256M Stage1 - Q3 2027, Stage 2 - Q4 2030 300 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date May 2029 → Stage1 - Q3 2027, Stage 2 - Q4 2030 2025-05-06 2026-10-06
Substations named SOUTH CREEK → FARMVILLE; PAMPLIN; SOUTH CREEK; WILLOW BROOK DP; ZEUS 2025-05-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 14 - DOM Supplemental Projects - Presentation p. 7
Dominion Transmission Zone: Supplemental Customer Load Request “north of Dominion South Creek 115kV substation”
115kV
2025-05-06 TEAC
Item 09 - DOM Supplemental Projects p. 3
Dominion Transmission Zone: Supplemental Customer Load Request “located north of Dominion’s South Creek 115kV substation”
115kV