Corey

Named in 2 PJM planning documents for 3 projects, from September 19, 2025 to July 17, 2026.

Existingdescribed as
AEPzone
—kV as printed
3mentions

PJM interconnection queue

A PJM queue substation page has the same name: Corey (MI) — 3 queue requests filed, 1 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hartford - Valley - Corey 138kV Rebuild
AEP-2023-IM011
Conceptual $162.85 M 09/23/2031 Not printed 2026-07-17
SRRTEP Western
Corey - Pigeon River 69kV rebuild
AEP-2023-IM012
Conceptual $43.358 M 09/27/2029 Not printed 2026-07-17
SRRTEP Western
Calvin Switch, MI
AEP-2025-IM009
Not printed Not printed Not printed Not printed 2025-09-19
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-07-17 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 19
Corey - Pigeon River 69kV rebuild “Station and P&C upgrades to accomodate the main line rebuild.”
2026-07-17 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 23
Hartford - Valley - Corey 138kV Rebuild No role wording
2025-09-19 SRRTEP Western
Item 06 - AEP Supplemental Projects p. 5
Calvin Switch, MI No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this