Trabue

Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to November 14, 2025.

Existingdescribed as
AEPzone
138 kV, 69kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Roberts-Wilson 138kV line “in & out” of Milepost 138kV
b3955.1
Not printed $12.17 M 06/01/2030 Not printed 2025-11-14
SRRTEP Western
Roberts-Wilson 138kV line “in & out” of Milepost 138kV Not printed $12.17 M 06/01/2030 Not printed 2025-10-17
SRRTEP Western
Columbus, OH
AEP-2023-OH047 · s3213.1-.6
Engineering $12.05 M 04/15/2024 33.5 MVA 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 73
Columbus, OH “Remote end work to accommodate the above work at Cole, Roberts, & Trabue”
138 kV
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 42
Roberts-Wilson 138kV line “in & out” of Milepost 138kV No role wording
69kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 37
Roberts-Wilson 138kV line “in & out” of Milepost 138kV No role wording
69kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 73
Columbus, OH “Remote end work to accommodate the above work at Cole, Roberts, & Trabue”
138 kV