Substation Scout

Davidson

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
AEPzone
138/69 kVkV as printed
2mentions

Also printed as: Davidson station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Columbus, OH
AEP-2023-OH047 · s3213.1-.6
Engineering $12.05 M 04/15/2024 33.5 MVA 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 73
Columbus, OH “Install a new 138/69 kV transformer at Davidson station”
138/69 kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 73
Columbus, OH “Install a new 138/69 kV transformer at Davidson station”
138/69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this