Poth station

Named in 3 PJM planning documents for 1 project, from October 18, 2024 to October 8, 2025.

Existingdescribed as
AEPzone
—kV as printed
3mentions

Also printed as: Poth

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone M-3 Process Columbus, OH
AEP-2023-OH004 · s3577.1-.3
Conceptual $7.233 M 09/30/2026 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2025 RTEP p. 6
AEP Transmission Zone M-3 Process Columbus, OH “Poth station (s2639) replaced the distribution function of Etna Road.”
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 6
AEP Transmission Zone M-3 Process Columbus, OH “Poth station (s2639) replaced the distribution function of Etna Road”
2024-10-18 SRRTEP Western
Item 06 - AEP Supplemental Projects p. 11
AEP Transmission Zone M-3 Process Columbus, OH “Poth station (s2639) replaced the distribution function of Etna Road”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.