Substation Scout

Apple Grove

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Not stateddescribed as
AEPzone
138 kVkV as printed
2mentions

PJM interconnection queue

A PJM queue substation page has the same name: Apple Grove (WV, OH) — 3 queue requests filed, 1 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Apple Grove, WV
AEP-2022-AP014 · s3143.1-.7
Conceptual $215.8M Phase 1 – 12/15/2025, Phase 2 – 12/15/2029 450 MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 36
Apple Grove, WV No role wording
138 kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 36
Apple Grove, WV No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.