Mercers Bottom

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Newdescribed as
AEPzone
345 kVkV as printed
2mentions

Described as new: “Construct a new 345 kV Station (Mercers Bottom)” — source, page 36

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Apple Grove, WV
AEP-2022-AP014 · s3143.1-.7
Conceptual $215.8M Phase 1 – 12/15/2025, Phase 2 – 12/15/2029 450 MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 36
Apple Grove, WV “Construct a new 345 kV Station (Mercers Bottom)”
345 kV
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 36
Apple Grove, WV “Construct a new 345 kV Station (Mercers Bottom)”
345 kV